UPDATE 1-GE Vernova to remove some Vineyard Wind blades after quality checks

Reuters
2024-10-24

(Adds details from press release, background)

Oct 23 (Reuters) - GE Vernova will remove some turbine blades installed at the Vineyard Wind offshore wind farm off the coast of Massachusetts following quality checks prompted by the failure of a blade in July, the company said on Wednesday.

The company has been barred from producing power or resuming full construction at Vineyard Wind, the first major U.S. offshore wind development, since a turbine blade broke and sent debris into the water that washed up on nearby beaches.

The turbine maker

blamed a manufacturing flaw

for the break, and has spent months inspecting blades with ultrasound images and drones.

"Out of an abundance of caution, GE Vernova intends to remove some blades from the Vineyard Wind farm while strengthening other blades as needed to support the safety and operational readiness of this project," GE Vernova and Vineyard Wind said in a joint statement.

The companies also said they were granted approval this week to resume installation of new blades at the project once certain safety and operational conditions are met. They did not give a timeline for when they expect those conditions to be met.

Vineyard Wind is a joint venture between Avangrid

and Copenhagen Infrastructure Partners. Avangrid is a unit of Spain's Iberdrola .

(Reporting by Nichola Groom; Editing by Richard Chang)

((nichola.groom@thomsonreuters.com))

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10