US Court revises FERC order for NextDecade's LNG facility

Reuters
03-19
US Court revises FERC order for NextDecade's LNG facility

March 18 (Reuters) - NextDecade NEXT.O said on Tuesday that the U.S. Court of Appeals for the District of Columbia had revised its August 2024 judgment.

The revision sends the Federal Energy Regulatory Commission's (FERC) order regarding the first five liquefaction trains at the Rio Grande LNG Facility back for further review, while the order itself remains in place.

"We are pleased with today's revised court judgment, which ensures construction at the Rio Grande LNG Facility will not be impacted by the court," said chief executive officer Matt Schatzman.

(Reporting by Seher Dareen in Bengaluru; Editing by Pooja Desai)

((Seher.Dareen@thomsonreuters.com; If in India call +91 74832 70128;))

免責聲明:投資有風險,本文並非投資建議,以上內容不應被視為任何金融產品的購買或出售要約、建議或邀請,作者或其他用戶的任何相關討論、評論或帖子也不應被視為此類內容。本文僅供一般參考,不考慮您的個人投資目標、財務狀況或需求。TTM對信息的準確性和完整性不承擔任何責任或保證,投資者應自行研究並在投資前尋求專業建議。

熱議股票

  1. 1
     
     
     
     
  2. 2
     
     
     
     
  3. 3
     
     
     
     
  4. 4
     
     
     
     
  5. 5
     
     
     
     
  6. 6
     
     
     
     
  7. 7
     
     
     
     
  8. 8
     
     
     
     
  9. 9
     
     
     
     
  10. 10