Mineral Resources (ASX:MIN) resumed haulage on the haul road at its Onslow Iron project on March 21, following discussions with regulator WorkSafe Western Australia regarding controls and risk mitigation, according to a Monday filing with the Australian bourse.
The haul road upgrade remains on track for completion in the first quarter of fiscal 2026, the filing said.
Additionally, the company's transhipper, MinRes Rosily, started operations at the Port of Ashburton on March 22, raising the project's transhipping capacity to 28 million tonnes per annum, the filing added.
The company reaffirmed its fiscal 2025 volume guidance for Onslow Iron.