长实(01113.HK)安达臣道首置盘传缺数条钢筋 屋宇署确认收到举报

阿斯达克财经
04 Oct 2024

《香港01》报道,长实集团(01113.HK) 正在兴建的观塘安达臣道首置盘,第三座缺少至少四条钢筋,地盘于上周六(28日)起停工。
屋宇署确认收到市民的举报,并在上月底确认涉事楼宇有六条横梁的钢筋配置与图则不一致,强调整体建筑物没有明显危险,已责成结构工程师及注册承建商提交报告,要署方满意有关报告后才可复工。

长实回应指,有关楼宇的扎铁及钢筋工序尚在进行中,并未完成,驻地盘结构工程师亦未检测。(mn/k)(港股报价延迟最少十五分钟。沽空资料截至 2024-10-03 16:25。)

AASTOCKS新闻

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.