Q: Can you provide more details on the localized geotechnical issue at QB2 and its impact on copper grades for the second half of the year? A: Jonathan Price, CFO, explained that the geotechnical issue is related to access to higher-grade areas due to a ramp issue. Shehzad Bharmal, SVP of Operations, added that the issue is being addressed with reorientation and additional support, expecting minimal impact on 2025 and 2026 grades. The second half of 2024 will see slightly lower grades, but full access is expected by early next year.
Q: Regarding your near-term growth projects, in what order will they be prioritized, and what are the key attributes for ranking them? A: Jonathan Price, CFO, stated that projects are managed as a portfolio with different risk-return characteristics. Highland Valley's mine life extension is prioritized due to its timeline, with Zafranal and San Nicolas following, depending on study outcomes. The focus is on balancing risk and reward.
Q: Can you clarify the capital requirements for sustaining capital and capitalized stripping, and how does this relate to development CapEx for 2025? A: Jonathan Price, CFO, mentioned that the $1 billion to $1.2 billion range is for sustaining capital and capitalized stripping. Development CapEx for projects in advanced stages is around $500 million annually, expected to continue through 2025.
Q: What are the key findings from the independent review of the QB project, and do you have the right team in place for future growth? A: Jonathan Price, CFO, confirmed that Teck is building a world-class project management team. Karla Mills, Head of Project, highlighted learnings such as increased geotechnical drilling and conservative assumptions on labor productivity and inflation. These are being integrated into future projects.
Q: What is the outlook for the zinc market, considering current TC/RC levels and global smelter output? A: Ian Anderson, Chief Commercial Officer, noted that zinc is in deficit due to mine shutdowns and disruptions. Low TCs reflect this deficit, with stable premiums in finished metal. A slight deficit is expected for 2024 and the first half of 2025.
For the complete transcript of the earnings call, please refer to the full earnings call transcript.
This article first appeared on GuruFocus.Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.