Operations
- Outstanding production from Sangomar with 75 Mboe/day produced in the quarter, driving record full-year production of 194 MMboe (530 Mboe/day), at the top end of the 2024 full-year production guidance range.
- Quarterly production of 51.4 MMboe. (559 Mboe/day), down 3% from Q3 2024 due to lower seasonal demand at Bass Strait and an unplanned shutdown at Pluto, partly offset by increased production at Sangomar.
- Quarterly revenue of $3,470 million, down 6% from Q3 2024 primarily due to lower seasonal demand at Bass Strait, partly offset by higher third-party LNG trades.
- Sold 33.6% of produced LNG at prices linked to gas hub indices in the quarter (12.8% of total equity production), realising a 31% premium compared to oil-linked pricing.
Projects
- The Scarborough Energy project was 78% complete at the end of the quarter, with the final Pluto Train 2 modules arriving at the Pluto LNG site in December. The project remains on target for first LNG cargo in 2026.
- The Trion project was 20% complete at the end of the quarter, with construction of the floating production unit commencing in November. First oil is targeted for 2028.
- Continued construction of the Beaumont New Ammonia project with Phase 1 of the project on track for start up in the second half of 2025.