Feb 19 (Reuters) - Rio Tinto PLC RIO.L:
FINAL RESULTS
FY25 PRODUCTION GUIDANCE IS CONSISTENT WITH OUR INVESTOR SEMINAR, RELEASED ON 4 DECEMBER
IN 2025 EXPECT SHARE OF CAPITAL INVESTMENT TO BE $11 BILLION
SEES 2025 PILBARA IRON ORE UNIT CASH COSTS $23.0-24.50 PER WMT
MID-TERM GUIDANCE FOR OUR SHARE OF CAPITAL INVESTMENT IS $10 TO $11 BILLION
SEES 2025 COPPER C1 UNIT COSTS 130-150 US CENTS PER LB
IN 2025, EXPECT OUR ONGOING EXPLORATION AND EVALUATION EXPENSE TO BE $1.0 BILLION
CONSTRUCTION OF PRIMARY CRUSHER 2 IN OYU TOLGOI PROGRESSING TO PLAN & REMAINS ON TRACK TO BE COMPLETED BY THE END OF 2025
SIMFER MINE IS ON TRACK TO DELIVER FIRST PRODUCTION AT THE MINE GATE IN 2025
TOTAL LOSSES FROM ALL FOUR CYCLONES ALONG PARTS OF PILBARA COASTLINE ANTICIPATED TO BE AROUND 13 MILLION TONNES
Further company coverage: RIO.L
((Reuters.Briefs@thomsonreuters.com;))
Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.