Q: Have the permits for the mine plan in 2025 been submitted yet? A: Yes, the permits were submitted on November 11th with the full support of the state government. We expect feedback from the Federal government in the first half of 2025. (Respondent: CEO)
Q: Will the strip ratio remain consistent in 2025, and how will it affect the mine plan? A: The strip ratio will remain consistent, and our production will not be interrupted in 2025. We have invested in a redesign to maintain production through 2024 and 2025. (Respondent: CEO)
Q: How will the grades be impacted next year? A: Grades depend on the pit location, with varying grades throughout. Recovery improvements have been positive, but as we go deeper, the recovery profile changes, which will be considered in our 2025 production planning. (Respondent: CEO)
Q: Can you provide an update on the South Railroad project submissions? A: We have received feedback from the Bureau of Land Management and are incorporating it into the next draft. We aim to have all submissions completed by year-end. (Respondent: CEO)
Q: Will the exploration results impact the current permitting effort or the near-term mine plan? A: The exploration results will not impact the current permitting process or the near-term mine plan. They will be incorporated into the long-term mine life and future expansions. (Respondent: CEO)