Cipher Mining (CIFR) acquired a 250-acre data center site in West Texas with a capacity of up to 100 megawatts for $4.1 million.
A variable fee of $1.5 per megawatt hour will be charged for the initial five years after the site gets connected to the electrical grid, the company said Tuesday in a statement.
The site, called Stingray, has regulatory approvals and a facility extension agreement with Oncor, an electric transmission and distribution company in Texas, Cipher Mining said. Anticipated availability of power consumption is H1 2026.
Shares of Cipher Mining fell 10% in recent Tuesday trading.