SINGAPORE, Jan 10 (Reuters) - Operators at Australia's key liquefied natural gas $(LNG)$ projects have announced the following planned maintenance dates for 2025, in which the start and end dates are approximate.
The information is according to statements on company websites and data from the Australia Energy Market Operator (AEMO).
Operator | LNG Facility | Scope of shutdown or maintenance | Start date | End date |
---|---|---|---|---|
Chevron CVX.N | Gorgon | Greater than half of an LNG train but not greater than one LNG train | June 1 | July 5 |
Inpex Corp 1605.T | Ichthys | Two LNG trains | Aug 16 | Oct 8 |
Woodside WDS.AX | North West Shelf | One LNG train | May 9 | May 16 |
One LNG train | May 19 | May 28 | ||
One LNG train | May 31 | June 9 | ||
ConocoPhillips COP.N | APLNG | Half a LNG train (Train 2) | March 1 | March 2 |
Half a LNG train (Train 1) | March 28 | March 29 | ||
Half a LNG train (Train 1) | July 17 | July 17 | ||
One LNG train (Train 2) | July 18 | July 21 | ||
Half a LNG train (Train 2) | July 22 | July 24 | ||
Half a LNG train (Train 1) | Sept 4 | Sept 4 | ||
One LNG train (Train 1) | Sept 5 | Sept 6 | ||
Half a LNG train (Train 1) | Sept 7 | Sept 16 | ||
Santos STO.AX | GLNG | Half a LNG train | March 31 | April 6 |
One LNG train | May 10 | May 11 | ||
One LNG train | June 16 | June 22 | ||
Half a LNG train | July 14 | Aug 7 | ||
Half a LNG train | Sept 16 | Sept 16 | ||
Shell SHEL.L | QCLNG | Capacity impacted (Train 2) | May 17 | June 7 |
(Reporting by Emily Chow)