Matsa Resources (ASX:MAT) reported a maiden ore reserve estimate of 309,000 tonnes of material at 4.59 gram per tonnes grade of gold for 46,000 ounces of gold for the Devon Pit mine in Western Australia, according to a Friday Australian bourse filing.
It completed optimizations and pit design using AU$3,500 per 3,000-per-ounce gold price.
Prefeasibility work at the mine resulted in a production target of 309,000 tonnes at 5.02g/t gold for 50,000 ounces.
The firm received draft processing agreements from multiple regional third-party processing facilities providing toll treat or ore purchase options and it is negotiating a preferred option, the filing said. It is also finalizing negotiations for a mining and haulage agreement.
It said the mine is fully permitted for mining operations to commence following receipt of approvals from the Department of Water and Environmental Regulation, as well as from the Department of Energy, Mines, Industry Regulation and Safety.
免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。