Glencore said production for 2024 was in line with its guided ranges after a stronger second-half performance. Here is what it had to say:
On 2024 production:
"2024 production volumes were delivered within our guidance ranges (unchanged from the beginning of the year), reflecting stronger second half (H2) performances across our key commodities. Copper production was 26kt higher in H2 (+6% vs H1), supported by Antapaccay's recovery from H1 geotechnical issues and higher grades at KCC. In zinc, H2 volumes jumped 71kt (+17% vs H1), reflecting increased contributions across the board, including from Kazzinc, Mount Isa and Antamina. In coal, energy volumes increased 5.2Mt in H2 in line with operational and logistical improvements in Australia and South Africa, while Steelmaking coal added 13.1Mt in H2 (a near-fivefold increase vs H1), reflecting the 12.5Mt contribution from EVR."
On copper:
"On a like-for-like basis, removing 15,000 tonnes of Cobar (sold in June 2023) volumes from the prior period, own sourced copper production of 951,600 tonnes was 43,500 tonnes (4%) below 2023. This reflected lower planned production at Antapaccay and Collahuasi, further impacted by geotechnical-related delays at Antapaccay and lower grades and unplanned mill downtime at KCC. H2 2024 copper production of 489,000 tonnes was 26,400 tonnes (6%) higher than H1 2024, mainly reflecting improved KCC production due to higher-grade ores, higher than planned run-rates at Mutanda and increased Mount Isa copper production, following a regional flooding event earlier in the year."
On zinc:
"Own sourced zinc production from the zinc department itself (i.e. excluding Antamina) was 51,000 tonnes (7%) higher than 2023. Overall own sourced zinc production of 905,000 tonnes was broadly in line with 2023, reflecting lower zinc tonnes from Antamina (64,500 tonnes), given its expected copper/zinc mine sequence during the year, largely offset by the ramp up of Zhairem (Kazzinc, up 53,600 tonnes). H2 2024 zinc production of 487,800 tonnes was 70,600 tonnes (17%) higher than H1 2024."
On nickel:
"Excluding KNS, own sourced nickel production of 77,300 tonnes was 6,900 tonnes (10%) higher than 2023. Overall own sourced nickel production of 82,300 tonnes was 15,300 tonnes (16%) lower than 2023, reflecting KNS's transition to care and maintenance (22,200 tonnes) in Q1 2024, partially offset by recovery from the INO supply chain constraints seen in the base period (3,700 tonnes) and higher production from Murrin Murrin (3,200 tonnes)."
On ferroalloy:
"Attributable ferrochrome production of 1,166,000 tonnes was in line with 2023."
On coal:
"Steelmaking coal production of 19.9 million tonnes mainly reflects Canadian steelmaking coal production of 12.5 million tonnes, representing the Elk Valley Resources $(EVR)$ business acquired in July 2024. Australian steelmaking coal production was consistent year over year."
"Energy coal production of 99.6 million tonnes was down 6% on 2023, reflecting the progressive impact of scheduled mine closures, longwall moves in Australia in 2024, export rail constraints in South Africa and a combination of permit delays, community blockades and unusually heavy rain at Cerrejon."
On oil:
"Entitlement interest oil production of 4.0 million boe was 0.8 million boe (16%) lower than 2023, largely due to natural field declines."
Write to Adam Whittaker at adam.whittaker@wsj.com
(END) Dow Jones Newswires
January 30, 2025 06:08 ET (11:08 GMT)
Copyright (c) 2025 Dow Jones & Company, Inc.
免责声明:投资有风险,本文并非投资建议,以上内容不应被视为任何金融产品的购买或出售要约、建议或邀请,作者或其他用户的任何相关讨论、评论或帖子也不应被视为此类内容。本文仅供一般参考,不考虑您的个人投资目标、财务状况或需求。TTM对信息的准确性和完整性不承担任何责任或保证,投资者应自行研究并在投资前寻求专业建议。